What is the next action a project manager should take when a dependency causes potential delays?

Study for the WGU ITEC2109 D324 Exam. Engage with interactive quizzes, multiple-choice questions, and detailed explanations to boost your readiness. Enhance your knowledge for success!

In a project management context, when a dependency causes potential delays, the next logical action is to update the project timeline. This is important because a delay in one area can impact the overall schedule and timeline of the project. Updating the timeline allows the project manager to reflect these changes and helps in identifying how the delay affects subsequent tasks and deliverables.

By adjusting the timeline, the project manager can also communicate new deadlines to the team and ensure that everyone is aligned with the revised schedule. This proactive approach is preventive in nature, enabling teams to adapt to changes more efficiently and reduce disruption to the project flow.

While communicating with stakeholders is also a crucial part of project management, the immediate action in response to a potential delay caused by a dependency should focus on updating the timeline to facilitate further planning and reassessment of project tasks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy