What is the project team developing if they discuss operational training and a go-live date?

Study for the WGU ITEC2109 D324 Exam. Engage with interactive quizzes, multiple-choice questions, and detailed explanations to boost your readiness. Enhance your knowledge for success!

The project team is developing a transition plan when they focus on operational training and a go-live date. A transition plan is a crucial document that outlines how a project will move from development and testing to production and operational use. Discussing operational training indicates that the team is preparing individuals to effectively use the new system or process, ensuring they have the skills and knowledge required.

The mention of a go-live date further emphasizes that the team is strategizing on the transition from one state to another, especially since the go-live date is the moment when the new system becomes operational. This planning helps in mitigating risks associated with the transition and ensures that all stakeholders are prepared for the changeover, thus confirming that the development of a transition plan is indeed the focus of their discussions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy